As of October 6, the following progress has being made:

  • 34.74% in the excavation of the Control works and spillway structure.
  • 72.22% in the excavation of the fourth terracing of the Powerhouse.
  • 5 % in the excavation of the third terracing of the Surge gallery.
  • 87% in the excavation of the plinth.
  • 11% of the dam wall material has already been placed (Dam works).

 

  • The placing of material on the dam wall continued. The works has an advance of 5%.
  • On March 10, the first phase of the cofferdam was complete.